Dualization of Bannu Miranshah Ghulam Khan Road, District North Waziristan P-I 25Km PDWP 31-10-2022.
Approved Cost : Original 9726.88 01-07-2022
Revised 9549.14 06-12-2022
Allocation CFY : 266.66
Remarks : Work order issued for package 1 & 4 on 20-07-2022
For Package 2,3,5 no bidder was technically qualified.
Design Consultant M/S Pavron
Subject Scheme is not reflected In Current ADP 24-25