Construction of Road from Balambat Timergara to Kalpani Maidan Link Road, District Dir Lower (10km)
Administrative Approval: = 318.690 (M) / Dated: 09/02/2015
Administrative Approval (Revised): = 689.999 (M) / Dated: 27/02/2018
Length of Road: = 10.0 Km
Date of Commencement: = September 2015
Date of Completion: = June 2025
Up to Date Expenditure: = Rs. 500.225 (M)
Allocation CFY: = Rs. 125.231 (M)
Utilization: = 100 %
Design Consultants: = MS ACE
Supervisory Consultants: = MS CEC
Physical Progress: = 90 %
Financial Progress: = 72 %
PDWP = 16/06/2022