CONSTRUCTION OF ROAD CONNECTING SUB-DIVISION WAZIR TO BANNU CIRCULAR ROAD BANNU Total length = 43 Km

Contract Cost                            :             Rs. 447.925 Millions
2nd Revised PC-I Cost               :             Rs. 514.124 Millions
TS Cost                                      :             Rs. 568.129 Millions
V.O- 1 Cost                                :             Rs. 483.677 Millions
% Below on Contract Cost        :             23.73  %
Date of Commencement            :           July 5th,2021
Date of Completion                  :            January 4th ,2024
Client                                        :            PKHA
Supervisory Consultant            :            NESPAK
Design Consultant                    :           A.A.ASSOCIATES
Contractor                                 :            Al Mehreen Enterprise JV ZMEG
PACKAGE Details 
Package Length                         :            7.72 KM
Carriageway Width                    :   7.30 Meter
Shoulder width                          :            2.00 Meter
No. of Lanes                              :           02 No.
Design Speed                             :           80 Km/hr
Contract Cost                            :             Rs. 311.123 Millions
2nd Revised PC-I Cost               :             Rs. 357.745 Millions
TS Cost                                      :             Rs. 324.682 Millions
V.O- 1 Cost                                :             Rs. 324.682 Millions
% Below on Contract Cost      :               17.22  %
Date of Commencement          :             April 26th,2021
Date of Completion                  :            October 25th,2023
Client                                         :            PKHA
Supervisory Consultant           :            NESPAK
Design Consultant                    :           NESPAK
Contractor                                :            Khyber Grace Pvt Ltd.
PACKAGE Details 
Package Length                         :            4.30  KM
Carriageway Width                    :   7.30 Meter
Shoulder width                          :            2.00 Meter
No. of Lanes                              :           02 No.
Design Speed                             :           80 Km/hr
Contract Cost                            :             Rs. 675.387 Millions
2nd Revised PC-I Cost               :             Rs. 776.592 Millions
TS Cost                                      :             Rs. 892.488 Millions
V.O- 1 Cost                                :             Rs. 881.521 Millions
% Below on Contract Cost        :            12.77  %
Date of Commencement          :             July 5th,2021
Date of Completion                  :            January 4th ,2024
Client                                         :            PKHA
Supervisory Consultant           :            NESPAK
Design Consultant                    :           NESPAK
Contractor                                :            Al Mehreen JV ZMEG
PACKAGE Details 
Package Length                         :            5.70 KM ( 2 No. Bridges)
Carriageway Width                    :   7.30 Meter 
Shoulder width                          :            2.00 Meter
No. of Lanes                              :           02 No.
Design Speed                             :           80 Km/hr
Contract Cost                            :             Rs. 447.925 Millions
2nd Revised PC-I Cost               :             Rs. 514.124 Millions
TS Cost                                      :             Rs. 568.129 Millions
V.O- 1 Cost                                :             Rs. 483.677 Millions
% Below on Contract Cost        :             23.73  %
Date of Commencement            :           July 5th,2021
Date of Completion                  :            January 4th ,2024
Client                                        :            PKHA
Supervisory Consultant            :            NESPAK
Design Consultant                    :           A.A.ASSOCIATES
Contractor                                 :            Al Mehreen Enterprise JV ZMEG
PACKAGE Details 
Package Length                         :            7.72 KM
Carriageway Width                    :   7.30 Meter
Shoulder width                          :            2.00 Meter
No. of Lanes                              :           02 No.
Design Speed                             :           80 Km/hr
 
Contract Cost :                  Rs.1726.667 Million
 
Date of Commencement :       20/09/2022
 
Date of Completion :               19/09/2025
 
Client:                                            PKHA
 
Supervisory Consultant:           NESPAK
 
Design Consultant:                    NESPAK 
 
Contractor :                        M/S AL-MEHREEN
                                                ENTERPRISES