Rehabilitation of Shahra-e-Tanawal (30 Kms) in District Haripur ADP (compact) No. 1128/210557 (2022-23)
PROJECT BRIEF
A.A / PC-1 Cost : Rs. 200.000 (M) dated 11-05-2022
CFY Allocation : Rs. 0.000 (M)
CFY Releases : Rs. 30.000 (M)
Up to Date Expenditure : Rs. 0.000 (M)
Up to Date Progress : 10.000 %
Date of Commencement : February 2023
Date of Completion : February 2024
Contractors : M/S Syed Tayyab Hussain Shah & Sons