Widening & Improvement of Tarnawa To Kohala Bala Road ( 34 km ) District Haripur (ADP No.1545/170629 2022-23 )
PROJECT BRIEF
Original PC-I Cost : Rs. 2232.195 (M), 11-02-2019
Revised PC-I Cost : Rs. 2221.880 (M), 01-06-2022
CFY Allocation : Rs. 80.00 (M)
CFY Releases : Rs. 40.00 (M)
Up to Date Expenditure : Rs. 1086.662 (M)
Up to Date Financial Progress : 48.90 %
Up to date Physical Progress : 50.22 %
Date of Commencement : May 2019
Date of Completion as per PC-I : May 2022
Date of Completion (EOT applied) : May 2024
Design Consultant : M/S AAA, Karachi, M/S PCE, Peshawar (JV)
Supervisory Consultant : M/S ACE Lahore, MS PAVRON, Islamabad (JV)
Contractors:
Package-I: From 0+000 to 9+000, M/S Z.S Construction (PVT) Ltd
Package-II : From 9+000 to 18+000, M/S Badi-uz-Zaman khan & Co. (PVT) Ltd.
Package-III : From 18+000 to 27+000, M/S Haji Raees Khan & Sons Construction Co.
Package-IV : From 27+000 to 33+860, M/S Haji Raees Khan & Sons Construction Co.