F/S detailed Engineering design for construction of Inter District road from Torghar to Buner District (length =25 km).
PROJECT BRIEF
A.A / PC-1 Cost : Rs. 4723.227 (M) Dated 06-12-2022
CFY Allocation : Rs. 0.001 (M)
CFY Releases : Rs. 0.001 (M)
Up to Date Expenditure : Rs. Nil
Up to Date Progress : 0 %
Date of Commencement: Nil
Date of Completion : june 30 2026
Design Consultant : M/S SPECTRA JV IAC (Indus Associated Consultants)