Construction of R.C.C Bridge on River Indus (01 Km Span) Near Kotkay Kandar District Torghar ADP No. 1494/220942 (2022-23)

PROJECT BRIEF 
 
Revised A.A / PC-1 Cost :  Rs. 9948.771 (M), dated 01-02-2023
CFY Allocation :  Rs. 0.001 (M)
CFY Releases :  Rs. 0.000 (M)
Up to Date Expenditure :  Rs. 763.734 (M) (1st Part Mobilization Advance)
Up to Date Progress :  0 %
Date of Commencement :  January-2023
Date of Completion :  January-2026
Design Consultant :  M/S AA Associates 
Supervisory Consultant :  M/S AA Associates (JV) CEC
Contractors :  M/S Al-Mehreen Enterprises – Hasas