UPgradation and Rehabilitation of Lawrancepur - Tarbela Road (25.2 KM)

THE PROJECT IS LOCATED IN ATTOCK AND HARIPUR DICTRICT AND SERVES AS CONNECTION ROUTE FOR TRAFFIC FROM DISTRICT SWABI, DISTRICT HARIPUR, DISTRICT ATTOCK, KAMRA CANTT AND ADJECENT AREAS TO MOTORWAY M1 AT GHAZI INTERCHANGE .  TOTAL LENGTH OF PROJECT IS 25.2 KM AND STARTED IN DECEMBER 2020. PROJECT IS DELAYED DUE TO  SHORTAGE OF FUNDS. UPTIL NOW PHYSICAL PROGRESS ACHIEVED IS 63.16% AND FINANCIAL PROGRESS IS 62.76%.  A TOTAL AMOUNT OF RS 1153.18  Million (including escalation )  IS CERTIFIED TO THE CONTRACTOR AGAINST TS COST OF RS 1837.56  Million. CONTRACTOR OF THE PTOJECT IS M/s Muhammad Khawaj Abbasi Engineer &  Contractor AND  CONSULTANT  IS M/s NESPAK Pvt. LTD.