Feasibility Study and Construction of Khwazakhela Bypass road (5.10km) District Swat.

SALIENT FEATURES:
Bid Cost:                          = 794.898 Million
PC-I Cost:                        = 1368.819 Million
Length of Road:                = 5.10 Km (3.56 Km + 1.54 Km)
Date of Commencement: =    November, 2022
Date of Completion:        =    November, 2026
Allocation During CFY: = Rs. 103.330 (M)
Release During CFY: = Rs. 34.100 (M)
Design /Supervisory Consultants:  M/S PAVRON Islamabad
Contractor:                      = MS NKB
Physical Progress: 39%
Financial Progress: 25.4 %
PDWP                                = 03/03/2022