Widening & Improvement and BT of Swari, Dewana Baba road (11 km) including RCC Bridge at Tangu,District Buner. (Road 11 km) (Bridge 75 meter) (R).

Administrative Approval: = 318.690 (M) / Dated: 09/02/2015
Administrative Approval (Revised): = 689.999 (M) / Dated: 27/02/2018
PDWP 31-03-2021 (High Priority)
Length of Road: = 10.0 Km
Date of Commencement: =    September 2015
Date of Completion:                    =    June 2026
Up to Date Expenditure:  =  Rs. 500.225 (M)
Allocation  CFY:                             = Rs. 125.231 (M)
Utilization: = 100 %
Design Consultants:   MS ACE
Supervisory Consultants:               = MS CEC
Physical Progress:                         90 %
Financial Progress:                       =  72 %