Improvement of 25 KM left over portion of Chukiyatan- Barawal-Shahi Road, District (Dir Upper).

140829 - Improvement of 25 KM left over portion of Chukiyatan- Barawal-Shahi Road, District Upper Dir PDWP 01-11-2021  (High Priority) 

Administrative Approval:                 = 7449.026 (M) / Dated: 09/02/2022
Administrative Approval (Revised): = 8990.776 (M) / Dated: 18/10/2023
Length of Road:                             = 44.0 Km
Date of Commencement: =    October 2022
Date of Completion:                     =     june 2026
Up to Date Expenditure:                =  Rs. 530.290 (M)
Allocation  CFY:                              = Rs. 103.333 (M)
Design Consultants:   MS CEC
Supervisory Consultants:  = MS CEC
Physical Progress: 15%