CONSTRUCTION OF ROAD FROM KRAPA TO SHAKARDARA DISTRICT KOHAT (LENGTH = 31.744 KM)
Name of the Project : IMPROVEMENT & REHABILITATION OF ROAD FROM KRAPA TO SHAKARDARA (31.744 KM) DISTRICT KOHAT ADP#1546/180163 (2022-2023).
PC-1 Cost : Rs. 2,266.33 Million.
B.O.Q Cost : Rs. 1,797.064 Million.
Revised Cost (Civil Works) : Rs. 1,698.015 Million
Revised Cost (Total Works) : Rs. 2,492.712 Million
Up to Date Expenditure : Rs. 1,297.033 Million.
Date of Commencement : P-I, 24/01/2019, P-II, 20/12/2018, P-III, 03/12/2018.
Original Date of Completion : P-I, 23/07/2021, P-II, 19/06/2021, P-III, 02/06/2021.
Revised Date of Completion : 30/06/2023
Executing Agency : Pakhtunkhwa Highways Authority (PKHA).
Design Consultant : Creative Engineering Consultant (CEC).
Supervisory Consultant : M/S NESPAK Ltd.
Contractors : (Package-01) M/S Fazal Karim & Co (Pvt) Ltd./Assigned to I.K.F Buraq Construction Company (Pvt) Ltd. : (Package-02) M/S Ghulam Muhammad Khan & Co/Assigned to Ali Associate.
Total Project Length 31.744 KM
Technical Standards AASHTO/NHA Specification
Pavement Type Flexible
ROW Width (Normal) 18.28 m
Formation Width 11.30 m
Pavement Width 7.30 m
Shoulder’s Width 2.00 m Permeable (each side)
Pavement Cross Slope 2%
Shoulder Cross Slope 4%
Design Speed for plain area 60 Km./Hr.
Design Speed for Hilly area 40 Km./Hr.
Design Speed for Sharp Hairpin bends 20 Km./Hr.
CARRIAGEWAY
AWC 05 cm
ABC 08 cm
WBM 25 cm
Granular Sub Base Course 15 cm
Improved Sub Grade Trenches (Widening) 30 cm to 45 cm
SHOULDERS
Permeable Shoulders 38 cm
PCC Shoulders (Saucer Drain) 15 cm
Granular Sub Base Course 15 cm
BRIDGES
P-1, RCC Bridge At Km 11+350 25 m Length (Single Sp