F/S & CONSTRUCTION OF CIRCULAR BYPASS ROAD, BANNU Total length = 41 Km

Contract Cost :             Rs. 555.868 Millions
PC-I Cost :                    Rs. 612.497 Millions
TS Cost :                       Rs. 639.152 Millions
V.O- 3 Cost :                 Rs. 629.997 Millions
% Increase against Contract Cost: 13.336 %
Date of Commencement :        02/11/2018
Date of Completion :                31/08/2022
Client:                                            PKHA
Supervisory Consultant:           NESPAK
Design Consultant:       A.A.ASSOCIATES
Contractor :             M/S KHYBER  GRACE(PVT) LTD 
PACKAGE Details :
Package Length:                       10.00 KM
Carriageway Width :                7.30 m
Shoulder width : RD 0+000  to 6+565= 1.50 m 
                         RD 6+565 to 10+000= 2.00 m
No. of Lanes:                         02 No.
Design Speed :                         80 Km/hr
Contract Cost :            Rs. 540.919 Millions
PC-I Cost :                    Rs.  605.061 Millions
TS Cost :                       Rs. 621.176 Millions
V.O-2 Cost :                  Rs. 621.955 Millions
% Increase against Contract Cost: 14.98 %
Date of Commencement :       02/11/2018
Date of Completion :         31/08/2022
Client:                      PKHA
Supervisory Consultant:           NESPAK
Design Consultant:       A.A.ASSOCIATES
Contractor :                 M/S KHYBER GRACE   (PVT) LTD 
PACKAGE Details :
Package Length:                       10.00 KM
Carriageway Width :                7.30 m
Shoulder width :                  2.00 m(Each side)
No. of Lanes:                   02 No.
Design Speed :                      80 Km/hr