F/S & CONSTRUCTION OF CIRCULAR BYPASS ROAD, BANNU Total length = 41 Km
Contract Cost : Rs. 555.868 Millions
PC-I Cost : Rs. 612.497 Millions
TS Cost : Rs. 639.152 Millions
V.O- 3 Cost : Rs. 629.997 Millions
% Increase against Contract Cost: 13.336 %
Date of Commencement : 02/11/2018
Date of Completion : 31/08/2022
Client: PKHA
Supervisory Consultant: NESPAK
Design Consultant: A.A.ASSOCIATES
Contractor : M/S KHYBER GRACE(PVT) LTD
PACKAGE Details :
Package Length: 10.00 KM
Carriageway Width : 7.30 m
Shoulder width : RD 0+000 to 6+565= 1.50 m
RD 6+565 to 10+000= 2.00 m
No. of Lanes: 02 No.
Design Speed : 80 Km/hr
Contract Cost : Rs. 540.919 Millions
PC-I Cost : Rs. 605.061 Millions
TS Cost : Rs. 621.176 Millions
V.O-2 Cost : Rs. 621.955 Millions
% Increase against Contract Cost: 14.98 %
Date of Commencement : 02/11/2018
Date of Completion : 31/08/2022
Client: PKHA
Supervisory Consultant: NESPAK
Design Consultant: A.A.ASSOCIATES
Contractor : M/S KHYBER GRACE (PVT) LTD
PACKAGE Details :
Package Length: 10.00 KM
Carriageway Width : 7.30 m
Shoulder width : 2.00 m(Each side)
No. of Lanes: 02 No.
Design Speed : 80 Km/hr