north Project

Home > Projects > NORTH

ADP NO. 1286/ 220397 - CONSTRUCTION OF ROAD FROM PATRAK TO THAL KUMRAT, DISTRICT UPPER DIR (44-KM)

Administrative Approval: = 7449.026 (M) / Dated: 09/02/2022
 
Administrative Approval (Revised): = 8990.776 (M) / Dated: 18/10/2023
 
Length of Road: = 44.0 Km
 
Date of Commencement: =    October 2022
 
 
Date of Completion: =    October 2025
 
Up to Date Expenditure: Rs. 530.290 (M)
 
Allocation  CFY: = Rs. 103.333 (M)
 
Design Consultants:   MS CEC
 
Supervisory Consultants:  = MS CEC
Physical Progress: 15%
 
Financial Progress: 11 %