ADP No.1275/180600_F/S, Design and Reconstruction of RCC Bridges, SH: Elai Bridge on (S-10) District Buner

Administrative Approval: = 668.596 (M) / Dated: 28/06/2019
 
Length/Span of Bridge: = 50 meter / 2 Span
 
Date of Commencement: =    October 2019
 
 
Date of Completion: =    December 2023
 
Project Cost: = Rs. 96.730 (M)
 
Up to Date Expenditure: Rs. 45.929 (M)
 
Allocation  CFY: = Rs. 323.596 © (M)
 
Design Consultants:   MS ACE
 
Supervisory Consultants:  = MS ACE
 
Physical Progress: 99 %
 
Financial Progress: 95 %