ADP SCHEME No. 1745/190556 (2020-21) “F/S, DESIGN & RECONSTRUCTION: OF 11 NOS BRIDGE: SH:LOT NO: 2 PACKAGE –V GWALERAI BRIDGE ON MATTA – FAZAL BANDA ROAD (S-17)
Name of the Project : ADP SCHEME No. 1745/190556 (2020-21) “F/S, DESIGN & RECONSTRUCTION: OF BRIDGES: SH: LOT NO: 2 PACKAGE –V GWALERAI BRIDGE ON MATTA – FAZAL BANDA ROAD (S-17)
Approved PC-1 Cost : Rs. 187.303 Million
Construction Cost (T.S) : Rs. 170.246 Millions
Up to Date Expenditures : Rs. 97.860 Millions
Date of Commencement : 1st June, 2021
Date of Completion : 30th November, 2023
Executing Agency : Pakhtunkhwa Highways Authority
Consultant : M/S Nespak Jv CEC (Pvt) Ltd
Contractors : M/s Mohmand Construction(Pvt.) Ltd.
Up-to-date Financial progress : 61.1 %
Up-to-date Physical Progress: : 65.0 %